DI-ADMN-81306
Program Protection Implementation Plan (PPIP)
The Program Protection Implementation Plan describes the contractor's methods for implementing the Government's Program Protection Plan and reporting protection inputs to the acquisition process.
Approval DateJanuary 25, 1993
AMSC NumberD6881
Preparing Activity—
Project Number—
OPROASD/C3I/CI&SCM(ASFO)
DTIC Applicable—
GIDEP Applicable—
Limitation—
Applicable Forms—
Approval Limitation—
Form VersionAPR 89
DID Formatdd_form_1664
963C CompliantNo
DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited.
Description & Purpose
3.1 This plan outlines and defines the contractor's implementation of the Government developed Program Protection Plan (PPP). The PPIP is the principle communications means for validation and approval by the DoD or Component Program Manager of the specific methods used by the contractor to (1) identify the means chosen to implement the PPP at contractor, sub-contractor, vendor controlled locations and (2) provide protection inputs to the system acquisition process. The principle purpose is to provide a method to ensure effective and efficient protection of essential program information, technologies and systems regardless of their location.
Application & Interrelationship
7.1 This DID contains the format and content preparation instructions for the Program Protection Implementation Plan (PPIP) resulting from the program protection requirements set forth in DoDI 5000.2, Part 5, Section F, "Program Protection Planning and Technology Controls". 7.2 This DID is applicable to all DoD acquisition programs regulated by DoDD 5000.1, DoDI 5000.2, and DoD 5000.2-M. 7.3 It is intended that all requirements contained herein shall apply to all applicable DoD acquisition programs through all program phases.
Preparation Instructions
10.1Content Requirements.The PPIP shall include the following:
10.1.1A section detailing the overall approachA section detailing the overall approach to the PPIP and the general methodologies which will be applied to the protection requirements indicated in the PPP.
10.1.2A section(s) describing fully the activities and methodologiesA section(s) describing fully the activities and methodologies planned to satisfy the PPP requirements and justification as to why these specific actions were chosen. Narratives, charts, diagrams, or matrixes shall be used to illustrate the methodology(s) chosen to establish effective and efficient countermeasures to program specific vulnerability(s). Explain these planned actions through all applicable milestones, at all contractor, sub-contractor or vendor controlled locations where the identified vulnerability(s) exist.
10.1.3A list of documents which applies as directive or guidanceA list of documents which applies as directive or guidance during execution of the PPIP. This list shall include pertinent legal, regulatory and other published or draft protection requirements applicable to the system under development. Program protection requirements and objectives shall be drawn from these documents.
10.1.4Details of all costs and resource requirementsDetails of all costs and resource requirements necessary to effectively and efficiently implement the applicable PPP requirements shall be included in the PPIP.