This report provides Government visibility into contractor direct and indirect expenditures under Research & Development and Services contracts, tracking planned and actual expenditures and labor hours against baseline values.
This report provides Government visibility into contractor direct and indirect expenditures under Research & Development and Services contracts. It tracks both planned and actual expenditures and labor hours against baseline values, and provides estimates at completion.
7.1 This DID contains the format and content preparation instructions for the data product generated by the specific and discrete task requirement as delineated in the contract.
7.2 This DID is applicable to time and material, research and development and other contracts where use of Cost Performance Reporting (CPR) or Cost/Schedule Status Reporting (C/SSR) is not appropriate and as an alternative to DI-FNCL-80331, Funds and Man-Hour Expenditure Report. It is not applicable to fixed-price contracts. It is acquired on a periodic (normally monthly) basis.
7.3 It is not intended that all the requirements contained herein should be applied to every contract or program phase. Portions of this DID are subject to deletion tailoring depending on the management requirements of the solicitation/contract in which it is applied.
7.4 This DID is related to DI-MGMT-80507A, Project Planning Chart (other than fixed price contracts), DI-FNCL-80003, Man-hours Expenditure Chart, and DI-FNCL-80331, Funds and Man-hour Expenditure Report.

Figure 1. FIGURE 1. Monthly funds & labor hour expenditure report.

Figure 1. FIGURE 1. Monthly funds & labor hour expenditure report - Continued

Figure 2. FIGURE 2. Funds expenditure graph

Figure 3. FIGURE 3. Hours expenditure graph