Support Equipment Installation Data (SEID)
The SEID provides the Government with information required for installing support equipment in existing or planned shipboard or shore-based facilities, including space, mounting, environmental, and safety requirements.
Approval DateOctober 6, 1987
AMSC NumberN4231
Preparing Activity—
Project Number—
OPRAS
DTIC Applicable—
GIDEP Applicable—
Limitation—
Applicable Forms—
Approval Limitation—
Form VersionJUN 86
DID Formatdd_form_1664
963C CompliantNo
DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited.
Description & Purpose
3.1 The SEID provides the Government with information required for the installation of SE in existing or planned shipboard/shore-based facilities.
3.2 It includes services, as well as space, mounting, environmental, special facility, and safety requirements relating to SE installation.
Application & Interrelationship
7.1 This data item describes data required by MIL-STD-2097(AS), paragraph 5.6.2.10.
7.2 This DID shall be applied to SE intended for installation in shipboard and/or shore-based facilities.
7.3 DID DI-ILSS-80118A, LSA-070, SERD is related and companion data.
7.4 This DID supersedes UDI-P-21006D.
Preparation Instructions
10.1Reference Documents.The applicable issue of the documents cited herein, including their approval dates and dates of any applicable amendments, notices, and revisions, shall be as specified in the contract.
10.2ContentSEID shall be furnished as required in MIL-STD-2097(AS), paragraph 5.6.2.10. The SEID required shall be legible and sufficiently detailed to enable site layout, preparation, and complete installation of the equipment by the procuring activity. The data shall include items of information as listed in paragraph 10.3.
10.3Items of InformationThe items of information required shall be prepared under the following headings:
a. Equipment Physical Requirements.
b. Space Requirements.
c. Mounting Requirements.
d. Servicing Requirements.
e. Safety Requirements.
f. Security Requirements.
10.3.1Equipment Physical Requirements.List as follows:
10.3.1.1Envelope dimensionsList length, width, and height of equipment, excluding packaging. If equipment folds for storage, list both storage and operating dimensions.
10.3.1.2WeightList weight of equipment, excluding packaging.
10.3.1.3Provide approximate center of gravity.
10.3.2Space Requirements.List as follows:
10.3.2.1Operator spaceList space required by personnel for operation of the equipment.
10.3.2.2Drawer removal spaceList space required for removal of drawers, opening of doors, or removal of access panels, if applicable.
10.3.2.3Access spaceList access space required at front, rear, above, below, and each side of the equipment.
10.3.2.4Additional space requirements required for units under test (UUTs) or ancillary test equipment.
10.3.2.4.1Identify UUT mounted test positione.g., on rack pullout work shelf/adjacent test bench/test roll cart.
10.3.2.4.2Indicate space required to move around the mounted UUT.
10.3.2.5Recommend position of test station in relation to other stations or associated equipment, as well as maximum and minimum separation permitted between related stations.
10.3.2.6Storage for ancillary test equipment and publications.
10.3.2.6.1Show test roll cart(s) operating and storage positions with securing features.
10.3.2.6.2Indicate storage requirements for ancillary test equipment and related publications.
10.3.3Mounting Requirements.List as follows:
10.3.3.1.1Rack mounting hole sizes and locating dimensions.(Refer to Figure 2, View 10-A.)
10.3.3.1.2Vibration isolator bottom mounting pad and hole pattern dimensions.(Refer to Figure 2, View 6-D.)
10.3.3.1.3Sequence of installation.
10.3.3.1.4Identify SE and GFAE/WRA (UUT) mounting dimensions or submit drawings.(Refer to Figure 1, Views 6-B, 6-C, 8-C, 9-B, 10-A.)
10.3.3.2Grounding and connection(s).
10.3.3.2.1Identify stud size, threads and wire size (AWG).(Refer to Figure 2 Side Elevation View).
10.3.3.3Special tools for installations.
10.3.4Servicing Requirements.List as follows:
10.3.4.1HydraulicType of fluid, pressure, flow rate, temperature, and hoses.
10.3.4.2Liquid coolant identification.
10.3.4.3WaterList pressure, flow, volume, temperature, and purity.
10.3.4.4SteamList pressure, flow, volume, temperature, and quality.
10.3.4.5Air or vacuumList pressure, flow, volume, temperature, purity, and vapor limitation.
10.3.4.6GasList pressure, flow, volume, temperature and type of gas.
10.3.4.7Air conditioningList pressure, flow, volume, temperature, and inlet duct size.
10.3.4.8Service System Flow Diagram
10.3.4.8.1Identify hoses/tubing, fittings, valves and sizes.
10.3.4.8.2Identify supply/return fittings and sizes of connections.
10.3.4.9Electric and Electronic input(Refer to Figure 2, Power Requirements Table I.) For each connection to the power service provided the following:
10.3.4.9.1Alternating Current(Refer to Para 10.4 Definitions)
Nominal Frequency - Hertz
Frequency Tolerance - Percent or Hertz
Quantity of Phases - Number
Type Connection - Wye or Delta and number of conductors
Nominal Voltage - Volts (rms)
Voltage Tolerance - Percentage
Voltage Transient Tolerance - Percentage
Voltage Transient Recovery Time - Seconds
Total connected Load and Power Factor - KW or KVA/decimal
Leakage current between any power service connection and chassis or ground connection - Milliamps
For equipment connections over 3.5 KVA add:
Worst case in-rush current - Amperes (peak)
Duration of in-rush current - Milliseconds
Harmonic current spectrum - Percent of Fundamental
Largest steady state current change - Amperes (rms)
Average connected load and power factor - KW/decimal
10.3.4.9.2Electric and electronic input - Direct Current.Voltage.
Voltage limits.
Amperage.
Ripple.
Identify positive and negative wiring.
10.3.4.10Heat dissipation of equipment(Use VA times 3.41 factor for BTU/HR.)
10.3.4.11Special facility requirements(Example: Ship's Gyro Information if applicable.)
10.3.4.12Installation Cabling Diagram(Refer to Figure 2, View 9-C or Figure 1, View 10-C.)
10.3.4.12.1Wiring color coding or line identification.
10.3.4.12.2Identify power plugs for compatibility with work bench receptacles.
10.3.4.12.3If required, identify interface devicee.g., transformer with mounting dimensions and connections from ships power and to test equipment. (Refer to Figure 2, View 7-D).
10.3.4.13Provide interconnecting wiring diagramfor multi-unit/rack systems, e.g., racks that are shipped separately. (Refer to Figure 2, View 10-B.)
10.3.4.13.1Identify cable (W1) and plugs (P1) connected to Jack (J1), etc.
10.3.5Safety Requirements.The provisions and equipment necessary to protect personnel and equipment including sound attenuation and laser requirements shall be stated.
10.3.6Security Requirements.State the security classification of the equipment being installed or the classification of any equipment used with the installed equipment.
10.4.1.1User Voltage.The nominal user input voltage (AC) is defined as the root-mean-square (rms) voltage applied. The nominal user input voltage (DC) is defined as the actual positive or negative voltage applied.
10.4.1.2User Voltage Toleranceis the maximum permitted departure from nominal user voltage during normal operations, excluding transient and cyclic voltage variations.
10.4.1.3Transient Voltage Tolerance.A voltage transient (excluding spikes) is a sudden change in voltage which goes outside the user voltage tolerance limits and returns to and remains within these limits within a specified recovery time after the initiation of the disturbance. The transient voltage tolerance is in addition to the user voltage tolerance limits.
10.4.1.4Transient Voltage Recovery Timeis the time elapsed from initiation of the disturbance until the voltage recovers and remains within the user voltage tolerance limits.
10.4.1.5Phases.Shipboard generators generally have their alternating-current circuits arranged to produce three-phase a.c. power with an angular relationship of 120 degrees. Single-phase a.c. power is also available aboard ship.
10.4.2.1Nominal Frequencyis the steady state, nominal user input frequency in Hertz (Hz).
10.4.2.2Frequency Toleranceis the maximum permitted departure from nominal frequency during normal operation, excluding transient and cyclic frequency variations.
10.4.3.1Steady State Currentis full load current in rms amps drawn by the user equipment.
10.4.3.2Start-Up or In-Rush Currentis the turn on, peak current drawn by the user equipment.
10.4.3.3Duration of In-Rush Currentis the time (in milliseconds) from sudden change in current (turn on) until the current recovers to steady state value.
10.4.3.4Harmonic Current Spectrumis the user equipment line currents from the 2nd up to 32nd harmonic (expressed in percent of the fundamental current). A harmonic frequency is a multiple of the fundamental frequency.
10.4.4.1Connected Loadis the nameplate rating of all equipment in the systems.
10.4.4.2Steady State Operating Loadis the continuous steady-state power in kW and kVA consumed by the user equipment.
10.4.4.3Transient Operating Loadis the sudden change in power (kW and kVA) consumed by the user equipment.
10.4.4.4Power Factoris the ratio of total watts per phase to the total rms volt-amperes per phase.
10.4.5Leakage Currentis the total rms current that passes from phase to ground with nominal voltage impressed at the nominal frequency.
Figures

Figure 1. Test bench harness sample data drawing.

Figure 1. Test bench harness sample data drawing - Continued.

Figure 1. Test bench harness sample data drawing - Continued.

Figure 1. Test bench harness sample data drawing - Continued.

Figure 1. Test bench harness sample data drawing - Continued.

Figure 1. Test bench harness sample data drawing - Continued.

Figure 2. Rack or console test equipment sample data drawing.

Figure 2. Rack or console test equipment sample data drawing - Continued.

Figure 2. Rack or console test equipment sample data drawing - Continued.

Figure 2. Rack or console test equipment sample data drawing - Continued.

Figure 2. Rack or console test equipment sample data drawing - Continued.

Figure 2. Rack or console test equipment sample data drawing - Continued.
Schema v3.0Community-maintained · Verify against ASSIST