DI-MGMT-81808
Contractor'S Risk Management Plan
The Contractor's Risk Management Plan monitors management, cost, and schedule of contract efforts related to a system and equipment, providing government with risk data for all associated risks.
Approval DateApril 21, 2010
AMSC NumberN9131
Preparing Activity—
Project Number—
OPRSH/PMS 408
DTIC Applicable—
GIDEP Applicable—
Limitation—
Applicable Forms—
Approval Limitation—
Form Version—
DID Formatdd_form_1664
963C CompliantNo
DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited.
Application & Interrelationship
—
Use & Relationship
The Contractor's Risk Management Plan will be used to monitor management, cost and schedule of the contract efforts relative to a system and equipment. This information will provide the government with risk data for all risks associated with the system/equipment. This Data Item Description (DID) contains the format, content, and preparation instructions for the data product resulting from the work task specified in the contract.
Preparation Instructions
1FormatThe plan shall be in contractor's format.
2ContentThe plan shall contain a cover and title page identifying the following:
2.2Plan document number/revision number or letter.
2.4Contractor name and address.
2.7Security classification, if classified.
2.8Distribution statement.
2.10Revision ControlThe plan shall contain a list of all revisions identifying the following information:
2.10.1Each revision number or letter.
2.10.2Date of each revision.
2.10.3Pages affected by each revision.
2.11Table of ContentsThe table of contents shall identify each major section title, paragraph number, and starting page number for each major section.
2.12ContentsThe plan shall address in depth each major section identified below:
2.12.4Risk Management Strategy and Process
2.12.5Responsible /Executing Organizational Component
2.12.6Risk Management Process and Procedures
2.12.7Risk Identification
2.12.9Risk Mitigation Planning
2.12.10Risk Mitigation Implementation
2.12.12Figure(s) and Table (s)
2.13Media requirementsThe plan shall be presented in electronic format MS Word version 2003-2007.