DI-MGMT-82049
Contractor Furnished Material (CFM) Report
This DID identifies Contractor Furnished Material (CFM) needed to accomplish contract Work Items that are not already on hand.
Approval DateJuly 5, 2016
AMSC NumberN9678
Preparing ActivitySH
Project NumberMGMT-2016-041
OPR—
DTIC Applicable—
GIDEP Applicable—
Limitation—
Applicable Forms—
Approval Limitation—
Form Version—
DID Formatfree_text
963C CompliantYes
DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited.
Application & Interrelationship
—
Use & Relationship
This DID will be used to identify Contractor Furnished Material (CFM) to accomplish the Work Items that are not already on hand.
This DID contains the format and content preparation instructions for the data product generated by the discrete task requirement as delineated in the contract.
Preparation Instructions
1Format.The report shall be in the contractor's format.
2Content.The report shall contain the following information:
2.2Contractor's purchase order number
2.3Description of material
2.5Date scheduled to be ordered
2.7Date required to meet production schedule
2.9A summary listing any problem areas
2.10Date submitted to the SUPERVISOR
2.12Drawing and piece number