DI-NDTI-81307A
First Article Qualification Test Plan and Procedures
Establishes the test procedures, test equipment, and inspection criteria the contractor will use for first article qualification.
Approval DateNovember 21, 2006
AMSC Number7649
Preparing Activity—
Project Number—
OPRNS/I522
DTIC ApplicableNo
GIDEP ApplicableNo
Limitation—
Applicable Forms—
Approval Limitation—
Form Version—
DID Formatdd_form_1664
963C CompliantNo
DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited.
Application & Interrelationship
—
Use & Relationship
To establish test procedures, test equipment, and the inspection criteria that will be used by the contractor for first article qualification.
This Data Item Description (DID) contains the format and content preparation instructions for the data product generated by the specific and discrete task requirement as delineated in the contract.
This DID supercedes DI-NDTI-81307.
Preparation Instructions
1Reference documents.None.
2Format:The plan shall be in the contractor's format.
3Content:This test plan shall include the following:
3.3Description of units to be tested.
3.4Test description to include the following:
3.4.1Step-by-step procedures which are to be followed by the operator when performing each test.
3.4.2Define readings to be taken, settings to be used, and description of the test equipment, including commercial identification.
3.4.3Drawings, schematics, photographs, etc, of noncommercial fixtures and testers necessary for test evaluation.
3.5Inspection criteria that defines the minimum performance requirements that the unit under test must meet in order to be considered acceptable to the Government.This shall include, as a minimum, worst case prime power input, worst case signal level and timing inputs, and signal level and timing outputs.