The Acceptance Test Report documents the results of HEMP-protection subsystem acceptance testing performed under MIL-STD-188-125, including test procedures, data, and analysis demonstrating compliance with pass and fail requirements.
The Acceptance Test Report applies to both parts of military standard MIL-STD-188-125, High-Altitude Electromagnetic Pulse (HEMP) Protection for Ground-Based Facilities Performing Critical, Time-Urgent Missions. This DID applies to fixed facilities in accordance with Part I (MIL-STD-188-125-1A) and to transportable systems in accordance with Part II (MIL-STD-188-125-2). This DID contains the format, content, and intended-use information for the data deliverable resulting from the acceptance-test tasks performed in accordance with section 4.4.2 and Appendices A and B of each part of MIL-STD-188-125, as applicable.
The purpose of acceptance testing the HEMP-protection subsystem (HPS) is to ensure that specified HEMP performance characteristics have been met. HEMP acceptance tests, conducted near the conclusion of a hardening construction or installation contract, are tests for the purpose of demonstrating that at least minimum performance requirements of the HEMP protection subsystem have been achieved before the HPS is accepted by the Government from the contractor.
The Acceptance Test Report documents the results of the HPS performance testing, and also describes the test-execution, data recording, analysis, inspection, and reporting procedures that were used by the contractor to assess and document these results. This report includes a discussion of recommended corrective actions, if needed. The report provides the means for the Government to evaluate and certify the HPS' performance results, in that the report demonstrates the HPS compliance with respect to MIL-STD-188-125's acceptance-test pass and fail requirements. The Department of Defense's HEMP-certification authority requires that a documented acceptance test report be submitted as part of a HEMP-certification request package for a facility or system.
If a portion of the HPS' components has already been acceptance tested by a previous test program, then documentation of those previous tests, including plans, reports, and test data, is attached as an appendix.
Data from the report will be applied to subsequent verification test-planning and testing efforts.