Acceptance Test Plan
The Acceptance Test Plan details the criteria, performance objectives, and list of tests to be performed by the contractor for acceptance tests on systems and equipment.
Approval DateNovember 14, 2006
AMSC Number7641
Preparing Activity—
Project Number—
OPRNS/DA02
DTIC ApplicableNo
GIDEP ApplicableNo
Limitation—
Applicable Forms—
Approval Limitation—
Form Version—
DID Formatdd_form_1664
963C CompliantNo
DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited.
Application & Interrelationship
—
Use & Relationship
The Acceptance Test Plan details the criteria, performance objectives and list of tests to be performed by the contractor for acceptance tests on systems and equipments.
This Data Item Description (DID) contains format and content preparation instructions for the data product generated by the specific and discrete task requirement as delineated in the contract.
This DID is applicable to contracts requiring preparation of an acceptance test.
This DID supersede DI-QCIC-80553.
Preparation Instructions
1Reference documents.None.
2Format.The plan shall be in contractor's format.
3Contents.The plan shall contain the following:
3.1Overview.Consists of a brief description of the objectives of the acceptance test plan, including flow diagrams, milestones, personnel participation, and security requirements. This section shall include the following:
3.1.1Flow diagram.A functional description of the acceptance test program using a block diagram portrayal of the functions that must be met to satisfy the total acceptance program. Functions shall be numbered 1.0, 2.0, 3.0, etc...
3.1.2Milestones.Identifies the start and expected completion dates of each test to be performed.
3.1.3Participation.Identifies the Government and Contractor participation roles and responsibilities.
3.1.4Security.Identify and state briefly any security measures of guidelines to be observed.
3.2Master test list.Lists all test to be accomplished in the order they are to be performed. Separated listings for each location shall be provided. This listings shall be include the following:
3.3Facility.Location where the acceptance test is to be performed.
3.4Item number.Number for each piece of equipment or item, test will be performed.
3.5Test description.Name and brief description of test to be performed.
3.6Parameters.The number of cycles the test will be performed and selected parameters to be observed.
3.7Equipment location.Current location of equipment to be tested or used in the acceptance test.
3.8Special tests.Provides a list of special or unusual tests and examinations necessary to verify satisfactory equipment performance to specifications.
4Equipment list.The equipment list shall list all equipment to be used in the acceptance test. The listing shall include the following:
4.1Test equipment.List all test equipment by:
4.2Support equipment.List all support equipment by.
4.3Special test equipment.List all special test equipment required to be designed or constructed for use on the program by:
5Validation procedure.An overview of the procedures that the contractor will use to validate the test results.