DI-SAFT-80105D
System Safety Program Progress Report (SSPPR)
The System Safety Program Progress Report (SSPPR) is used to cover periodic reviews of safety activities and to monitor progress of contractor system safety efforts.
Approval DateJuly 15, 2025
AMSC NumberF10583
Preparing Activity40 (AFMC/SE)
Project NumberSAFT-2025-005
OPR—
DTIC ApplicableNo
GIDEP ApplicableNo
Limitation—
Applicable Forms—
Approval Limitation—
Form Version—
DID Formatfree_text
963C CompliantYes
DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited.
Related
DI-SAFT-80101DI-SAFT-80102DI-SAFT-80106DI-SAFT-82085
Application & Interrelationship
—
Use & Relationship
The System Safety Program Progress Report (SSPPR) is used to cover periodic reviews of safety activities and to monitor progress of contractor system safety efforts.
a. This Data Item Description (DID) contains the content and format preparation instructions for the data product generated by the specific and discrete task requirement as delineated in the contract.
b. This DID is related to DI-SAFT-80101, System Safety Hazard Analysis Report (SSHAR); DI-SAFT-80102, Safety Assessment Report (SAR); DI-SAFT-80106, Health Hazard Assessment Report (HHAR), and DI-SAFT-82085, Hazard Tracking System (HTS) Data.
c. Do not use DI-ADMN-81250, Conference Minutes, in conjunction with this DID. (Copies of these DIDs are available online at http://quicksearch.dla.mil.)
d. This DID supersedes DI-SAFT-80105C.
Preparation Instructions
1Reference documentsThe applicable issue of the documents cited herein, including their approval dates and dates of any applicable amendments, notices, and revisions, shall be as specified in the contract.
2FormatThe SSPPR shall be in the contractor's format.
3ContentThe SSPPR shall include a description of the general progress made relative to the system safety program during the reporting period and the projected work for the next reporting period. The report shall contain the following information in narrative form:
3.1A brief summary of activities, progress, and status of the safety effort
3.1.1Significant achievements and problemsIt shall highlight significant achievements and problems.
3.1.2Progress toward completion of safety data items prepared or in workIt shall include progress toward completion of safety data items prepared or in work.
3.1.3Status toward completion of Level of Rigor (LOR) task activitiesIt shall include a status toward completion of Level of Rigor (LOR) task activities.
3.2Newly recognized significant hazards and significant changes in the degree of control on known hazards
3.3Inventory of identified hazardsInventory of identified hazards, with each hazard tabulated by sequence number, identified by the initial risk index value and revised risk index value after incorporation of hazard mitigation, action taken to date, and its action status: open, closed, or monitor. Include any hazards which the contractor believes cannot be reduced to an acceptable level of risk and will require managing activity action.
3.4Status of all recommended mitigation measures that have not been implemented and the date of hazard resolution
3.5Significant cost, schedule, and performance changes that impact the safety program
3.6Discussion of documents reviewed by safety during the reporting periodDiscussion of documents reviewed by safety during the reporting period. Indicate whether they were acceptable for safety content and whether or not inputs to improve the safety posture were made.
3.7Discussion of specific efforts for each unit of software to determine Software Criticality Index (SwCI)Discussion of specific efforts for each unit of software to determine Software Criticality Index (SwCI) as well as developing the artifacts documenting completion of LOR task activities.
3.8Proposed agenda for future system safety meeting(s)
3.9Minutes of the past system safety meeting(s)