DI-SESS-82453
SLM Option Aircraft Production Enhanced Status Report
Specifies the format and content for a report summarizing aircraft production status, including work stoppages and reasons for delay such as engineering, material, and production issues.
Approval DateSeptember 30, 2024
AMSC NumberN10500
Preparing ActivityAS
Project NumberSESS-2024-056
OPR—
DTIC Applicable—
GIDEP Applicable—
Limitation—
Applicable Forms—
Approval Limitation—
Form Version—
DID Formatfree_text
963C CompliantYes
DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited.
Application & Interrelationship
—
Use & Relationship
A report to summarize production status, highlight work stop, storage and reasons for delays such as Engineering, Material and Production.
This Data Item Description (DID) contains the format, content, and intended use information for the data product resulting from the work task described by the contract SOW.
Preparation Instructions
1Reference DocumentsThe applicable issue of the documents cited herein, including their approval dates and dates of any applicable amendments, notices, and revisions, shall be as specified in the contract.
2FormatUse format as defined below. If the element does not apply to the platform or project, put Not Applicable for that paragraph.
3ContentThe Report shall contain the following information/data, as applicable:
3.1Cover and title pageThe following information shall appear on the outside front cover and title page:
3.1.2Report number (contractor or government)
3.1.3Contractor's name, address, and commercial government entity code
3.1.4Contract number and contract line item number or sequence number (if applicable)
3.1.6Name and address of requiring government activity
3.1.7Security classification, downgrading and declassifying information, if applicable
3.2.1ContentFor the Aircraft Production detail, the Report shall contain the following information, as applicable:
3.2.1.6Reporting Custodian/ Wing Customer Name
3.2.1.8Scheduled Completion Date
3.2.1.10Current Date Customer Expects Delivery
3.2.1.11Reported Eval TAT
3.2.1.13Detailed Description of Items Currently Causing Delay
3.2.1.14Detailed Description of findings, inspections, issues, assessments and analyses
3.3.1ContentFor the Engineering detail, the Report shall contain the following information, as applicable:
3.3.1.8Disposition Status
3.3.1.11Engineering REI ECD
3.3.1.13Detailed Description of Items Currently Causing Delay
3.4.1ContentFor the Material detail, refer to the Purchase Request form attachment to the contract.